Project Overview

This spring, NDOT in partnership with the City of Reno and Granite Construction will begin two safety improvement projects.

The first is on Second Street from Keystone Avenue to Kietzke Lane and at the intersection of Arlington Avenue and Island Avenue in Reno. The second project is on Kietzke Lane from Mill Street to Galletti Way. Construction will begin in March and complete in summer 2019. Construction is weather permitting.

Drivers and pedestrians will see single lane closures, minor detours, parking restrictions and sidewalk closures. Construction will occur simultaneously on both projects.

 

Traffic Control Week of March 10

Beginning Tuesday, March 12 until approximately Friday, March 15,  Granite Construction will have eastbound and westbound daytime road closures at Second Street and Kuenzli Street, but  not at the same time for pedestrian safety improvements. Construction will begin on Monday with closures on Tuesday.  Please use signed detours. Business and emergency access will be maintained.

Project Details

Second Street from Keystone Avenue to Kietzke Lane and Arlington Avenue at Island Avenue

Improvements include: construction of enhanced pedestrian-accessible ramps; upgraded signs and striping; new crosswalks; LED lighting; traffic calming bulb outs; upgraded curbs and sidewalks; and a roundabout at Second Street and Giroux Street.

Kietzke Lane from Mill Street to Galletti Way

Improvements include: Bicycle and pedestrian safety improvements; construction of enhanced pedestrian and driveway ramps; minor pavement rehabilitation; sidewalk widening and intersection safety improvements.

1. Second Street at Winter Street
2. Second Street at Washington Street
3. Second Street at Bell Street
4. Second Street at Ralston Street
5. Second Street at Stevenson Street
6. Second Street at Arlington Avenue
7. Second Street at West Street
8. Second Street at Kuenzli Street
9. Second Street at Giroux Street
10. Second Street and Kietzke Lane
11. Arlington Avenue at Island Avenue.

Schedule and Traffic Control

Second Street

The team will begin demolition and underground improvements on the west end of the project near Keystone Avenue, Arlington Avenue and Kuenzli Lane in March.  Concrete crews will follow the demolition team and construct new pedestrian ramps. The team will move east in late April and May to construct the roundabout at Second Street and Giroux Street and pedestrian and sidewalk improvements at Second Street and Kietzke Lane. The project schedule is subject to change and is weather permitting.

Construction will predominantly take place Monday to Friday from 7 am to 5 pm.

Kietzke Lane from Mill to Galletti

Traffic control will include lane closures, sidewalk detours and a minor detour with the roundabout construction.

The team will remove the top layer of roadway on Kietzke Lane in March and begin sidewalk and driveway improvements in April. Traffic may be switched to one side of the roadway and switched back.  Concrete and paving crews will construct new driveways, sidewalk and pedestrian ramps in May and June. The project schedule is subject to change and is weather permitting.

The team will work evenings, Sunday to Friday from 7 pm to 6 am.

Traffic control will include lane closures, traffic shifts, sidewalk detours and temporary driveway closures. At least one access to businesses will be maintained at all times.